Monday, May 12, 2014

HAS-200 Modules 1-3 individually functioning

This is showing each module run through once successfully.

(Module 1)


(Module 2)



(Module 3)


(Module 4)




Friday, May 9, 2014

Week Six

Today was spent dialing in module 1-3 and  trying to get module 4 running, after a few sporatic runs and an attempt at restarting the PLC, we determined new batteries are needed, but the module 4 should run fin once the program is functioning.

(Capper working several time successfully)


(A Run Through of the Module 1-3)

Friday, May 2, 2014

Week Five

The continuous air lines were ran to the HAS-200 assembly line and blog was updated to date.
- Regulator for the continuous air system needs to be replaced.

Monday, April 28, 2014

Friday, April 25, 2014

Week Four

Calibrating module one, two and three. Module four has the OK light blinking red.

Friday, April 18, 2014

Week Three

Continued investigation of the HAS-200 and began calibration of the modules.

(Josh is gonna Love this)

(Video 1)

(Video 2)

(Video 3)


Friday, April 11, 2014

Week Two

Reviewed machine processes and developed a plan to make the HAS-200 fully operational. 
(The crew is busy working)
(Investigating Machine Processes)


Friday, April 4, 2014

Week One

Setup HAS-200 assembly line and get acquainted with the module configuration.

  • Tied together and leveled the modules 
  • Removed module 3's motor and replaced the belt and modified the drive pulley to prevent belt slip

(Module guide rails installed and aligned)
(HAS-200 Assembled)
(Being Supervised :-( )