Monday, May 12, 2014

HAS-200 Modules 1-3 individually functioning

This is showing each module run through once successfully.

(Module 1)


(Module 2)



(Module 3)


(Module 4)




Friday, May 9, 2014

Week Six

Today was spent dialing in module 1-3 and  trying to get module 4 running, after a few sporatic runs and an attempt at restarting the PLC, we determined new batteries are needed, but the module 4 should run fin once the program is functioning.

(Capper working several time successfully)


(A Run Through of the Module 1-3)

Friday, May 2, 2014

Week Five

The continuous air lines were ran to the HAS-200 assembly line and blog was updated to date.
- Regulator for the continuous air system needs to be replaced.